maybe the facility will get finished




McCarroll Construction sent a completion schedule to AppalCART.
Temporary power 2/9/2012
Storm Drainage reset SD near entry 3/2/2012
Site Water
Roof Drainage 4/4/2012
Curb & Gutter 4/6/2012
Asphalt binder 4/6/2012
stone 3/27/2012
top coat 4/27/2012
Fencing 4/15/2012
Facility Sign erection 4/13/2012
Rain Catchment 3/9/2012
Solar Collectors 4/8/2012
Air Compressor 3/16/2012
Interior trim epoxy floor quarter round 3/16/2012
Downspouts 4/6/2012
Interior Doors 3/16/2012
Interior Hardware 3/23/2012
Vinyl cove base 4/4/2012
Epoxy Floors 4/13/2012
final painting 4/1/2012
Fire ext. 4/11/2012
Residnetial Appliances 4/6/2012
Bus wash plumbing lines 3/30/2012
Bus lift 4/13/2012
Elevator 4/10/2012
Plumbing 2/17/2012
HVAC testing 4/4/2012
Electrical 4/15/2012
Generator 4/4/2012
Canopies
excavation Canopy B 3/6/2012
excavation Canopy C 3/13/2012
excavation Canopy D 3/14/2012
footings Canopy A 3/8/2012
footings Canopy B 3/8/2012
footings Canopy C 3/15/2012
footings Canopy D 3/16/2012
erection Canopy A 3/25/2012
erection Canopy B 4/1/2012
erection Canopy C 4/20/2012
erection Canopy D 4/20/2012
Painting Canopies 5/6/2012
Electric Canopies 4/20/2012
Decorative Trim A&B 4/6/2012
Decorative Trim C&D 4/21/2012
permanet power 4/2/2012
Inspection by Architect 4/11/2012
Final Clean 4/27/2012
Testing 4/20/2012
Punch List 4/22/2012
Turnover 5/1/2012